Yarwun Heat Battery Study Advances With ARENA Funding
Rondo and Rio Tinto have begun engineering a proposed 360 MWh Yarwun heat battery, supported by staged ARENA funding for industrial steam electrification.
Published · 3 min read

Rondo Energy and Rio Tinto have begun front-end engineering and design for a proposed 360 MWh thermal storage system at the Yarwun alumina refinery near Gladstone, Queensland. The Yarwun heat battery would supply industrial steam, with Australian Renewable Energy Agency funding progressing in stages rather than as an unconditional construction commitment.
In its October 21 announcement, ARENA confirmed an initial A$3.6 million for the engineering study. Successful completion would unlock up to A$38 million for deployment. A separate ceiling of A$33.3 million in conditional contingency support would be available only under defined circumstances, including specified cost-overrun and electricity-cost risks.
The study matters because alumina refining requires continuous process heat, while cheaper electricity may be available for shorter periods. Storing electricity as heat could help bridge that mismatch. The current milestone is engineering and evaluation; it does not establish that the proposed equipment has been built or commissioned.
What the Yarwun heat battery would deliver
ARENA identifies the proposed unit as having 78 MW of electrical charging capacity and 30 MW of thermal discharge capacity, with 360 MWh of thermal storage. These ratings describe electricity entering the system and heat leaving it. They are not a 30 MW electricity-export rating.
Rondo’s technology uses electricity to heat refractory brick, then releases the stored heat to produce steam or hot air. Its project announcement says the Yarwun study will assess integration into the refinery’s existing steam network and the technical and economic viability of replacing fossil fuels for part of its steam requirements.
Dividing the proposed 360 MWh storage capacity by the 30 MW thermal discharge rating gives a nominal 12 hours at that output. This simple calculation excludes operating losses and usable-capacity constraints. Continuous daily steam supply would also depend on recharging, dispatch strategy and the refinery’s wider heat-supply arrangements.
ARENA expects the project to reduce onsite carbon dioxide emissions by around 67,000 tonnes annually. That is a projected outcome for the proposed demonstration, not a measured reduction already achieved at Yarwun.
Onsite emissions savings also need to be distinguished from the emissions associated with purchased electricity. The eventual climate benefit depends on the power used to charge the system and the fossil-fuel heat displaced. The announcement does not provide a measured lifecycle assessment of the proposed installation.
Funding supports a demonstration with unresolved economics
The distinction between the initial study funding, subsequent deployment support and conditional contingency matters. Adding their maximum values together would obscure the different release conditions and could suggest money has already been paid for construction.
ARENA is backing the project through its Industrial Transformation Stream. The agency says large operating industrial facilities provide a setting to assess reliability, performance and integration before emerging heat technologies are adopted more widely.
For Yarwun, equipment sizing alone will not settle the investment case. Electricity procurement, charging schedules, steam requirements and integration with existing plant operations will determine whether the proposed system can provide an economically useful alternative to fossil-fuel heat.
The need to evaluate actual loads, integration and operating costs also underpins Microgrid Media’s guide to a microgrid feasibility study. Yarwun’s announcement concerns industrial thermal storage, with its own process requirements; it does not describe an islandable electrical microgrid.
A refinery with wider operating constraints
Rio Tinto’s Yarwun operations page says the company plans to reduce production by 40% from October 2026 because of tailings-capacity constraints. The company says that would extend the refinery’s expected life to 2035 while it works through options for its future.
The heat-storage study addresses a separate challenge: lowering emissions associated with steam production while maintaining reliable operations. For the Yarwun heat battery, the next meaningful milestones are completion of the engineering assessment, satisfaction of deployment-funding conditions and a confirmed path to construction.