Punta Lima Battery: Polaris Signs Trina Supply Contract
Polaris has signed Trina Storage for Punta Lima’s planned 35.7 MW, eight-hour battery, with deliveries scheduled for spring 2027 and operation targeted later that year.
Published · 3 min read

The Punta Lima battery project in Puerto Rico has moved into equipment procurement after Polaris Renewable Energy signed a supply contract with Trina Storage, the company announced October 20. Polaris now describes a single 35.7 MW system with eight hours of storage duration, with commercial operation targeted for the third quarter of 2027.
The company expects gross project spending of US$55 million to US$60 million, funded from cash on hand. Battery-container deliveries are scheduled for March and April 2027, leaving construction, integration and commissioning ahead before the system can provide contracted grid services.
Punta Lima battery contract advances an existing agreement
Polaris’s October 20 project update identifies the supplier as Trina Energy Storage Solutions (Singapore). The announcement’s new development is the executed equipment contract, following Polaris Power US’s June 5 execution of a storage standard-offer agreement with the Puerto Rico Electric Power Authority.
The project participates in Puerto Rico’s Accelerated Storage Addition Program, intended to add utility-scale batteries alongside existing generation. Polaris’s Punta Lima project page identifies its existing asset as a 26 MW wind farm in Naguabo. The wind-farm rating and the proposed battery rating describe separate equipment.
The supply award moves the battery beyond its earlier commercial framework into procurement. It does not establish that containers have arrived, construction is complete or the storage service is already available.
Physical power differs from contractual storage capability
The updated configuration needs careful reading. Polaris specifies one 35.7 MW battery with an eight-hour duration, while the standard-offer agreement identifies 71.4 MW of “Storage Capability” served through two four-hour delivery blocks.
Multiplying 35.7 MW by eight hours gives 285.6 MWh as an implied energy quantity. The same arithmetic results from 71.4 MW multiplied by four hours. These calculations explain the relationship between the disclosed figures; they are not an independently verified usable-energy rating.
The contractual figure should not be presented as 71.4 MW of simultaneous physical battery output. Polaris’s latest description explicitly identifies a single 35.7 MW system. Operating reserves, losses, degradation and the agreement’s measurement rules will affect actual service delivery.
Earlier independent coverage described the project under the 71.4 MW contract figure and a third-quarter 2026 operating target. The October release provides the newer equipment configuration and 2027 target; it does not explain the schedule change.
Costs and returns remain company projections
The US$55 million to US$60 million estimate includes the battery, medium-voltage transformer, tariffs and balance-of-plant work. It is an overall project estimate rather than a disclosed price for Trina’s equipment alone.
Polaris projects approximately US$12.5 million of first-year EBITDA once the project is constructed and fully operational. That is a management forecast, not achieved earnings, net income or cash available for distribution. The release does not provide a complete financial model supporting the estimate.
The company’s risk statement identifies equipment availability, permitting, interconnection approvals and contractor performance among the factors that could change costs or timing. The release does not identify a battery-cell chemistry or the detailed performance acceptance criteria attached to the supply contract.
Under the standard-offer agreement, Polaris Power US expects monthly fixed and performance-based payments for storage services, including capacity and grid support. The 20-year service term begins at commercial operation.
Microgrid Media’s reporting on Puerto Rico’s emergency orders provides historical context for the island’s reliability challenges. Its coverage of the battery procurement framework explains why acceptance testing, warranties and delivery obligations matter. Polaris has not said its Trina agreement uses that voluntary framework.
The Punta Lima battery now has a named equipment supplier and a delivery schedule. Its next substantive tests are container delivery, installation and verified operating performance against the contracted service requirements.