PJM Files Revised Backstop Proposal, Targets March 2027 Auction
PJM has filed revised reliability-backstop rules with FERC, proposing March 2027 bidding and new cost-allocation, collateral and exit obligations for large-load-driven capacity needs.
Published · 4 min read

PJM Interconnection filed an amended PJM backstop procurement proposal with the Federal Energy Regulatory Commission on October 29, 2026, seeking to restart a one-time capacity procurement for its 13-state electricity market after federal regulators delayed the original plan. The revised filing changes how costs, credit obligations and financial responsibilities would be assigned as data centers and other large customers increase demand.
The proposal would open bidding on March 1, 2027, against an earlier capacity shortfall of 6,831 MW for the 2028–2029 delivery year. PJM says it will recalculate the procurement target using updated forecasts and eligible bilateral supply contracts. Neither the target nor the launch date represents capacity already purchased or a procurement schedule approved by FERC.
What changes in the PJM backstop procurement
In its October 29 filing announcement, PJM identifies three central revisions: the method of assigning procurement charges, the collateral required from load-serving entities and the responsibility of those entities if they leave PJM’s market.
The filing is a substantive follow-up to FERC’s September 29 decision. As Microgrid Media reported when the original auction was postponed, FERC accepted the earlier tariff revisions for filing but suspended implementation for five months while examining unresolved issues. The October submission proposes answers to those issues; it does not erase the federal review.
That distinction is important for electricity buyers. A revised tariff proposal may reduce uncertainty about the operator’s preferred design, but the charges and procurement timetable remain subject to regulatory proceedings and the eventual tariff in force.
Cost allocation follows growth in large electricity loads
Under PJM’s revised approach, the allocation of backstop charges would be tied to firm large-load growth between actual summer 2026 peak demand and the forecast for the 2028–2029 delivery year. Electric distributors would report qualifying customer demand, with costs assigned across zones according to their contribution to that growth.
The mechanism is designed to connect the cost of additional capacity with the areas where major new demand is developing. It does not establish that every data center will receive a uniform bill or that PJM can directly set each customer’s retail tariff. Those outcomes also depend on the applicable utility, state regulator and customer arrangements.
In a September concurrence, FERC Commissioner Lindsay See emphasized that existing customers should not automatically bear costs created by new demand. PJM’s new allocation method responds to that concern, although the final allocation formula has not been approved in this latest filing.
Collateral and exit obligations address financial exposure
The proposal also revises credit requirements for load-serving entities responsible for backstop payments. PJM describes a lower uniform credit rate and updated payment terms intended to balance the expense of posting collateral against the risk that other market participants would absorb unpaid obligations.
Separately, a load-serving entity leaving the PJM market would remain responsible for its assigned backstop charges for the remainder of the commitment term, subject to the filing’s proposed provisions. That obligation matters because the procurement could support capacity commitments lasting up to 15 years, well beyond a single retail supply contract.
PJM would also remove an earlier exemption for certain municipal utilities and electric cooperatives and require at least a five-year plan for a peak-shaving adjustment opt-out. The revisions clarify when demand response and distributed energy resources can count as qualifying offsets, rather than treating every behind-the-meter battery as automatically eligible.
March bidding is proposed, not guaranteed
PJM’s new schedule calls for bidding to open March 1 and close March 28, 2027. The operator would determine final procurement targets and supply amounts on April 28 and post results on May 10. The proposal retains a maximum willingness to pay based on a megawatt-weighted average of $555 per MW-day.
The amount ultimately sought could be lower than the original 6,831 MW gap. PJM plans to update the reliability requirement and subtract qualifying new supply secured through executed bilateral contracts to avoid buying the same capacity twice.
The shortfall itself is a forward-looking capacity-auction measurement, not evidence of an ongoing 6.8 GW outage. PJM is attempting to secure future supply while preserving a separate route for large customers to arrange new generation directly.
The debate also differs from the federal large-load interconnection proceedings affecting multiple grid operators. Those cases focus on how major users connect to transmission systems; PJM’s backstop addresses whether sufficient generation capacity is available and who pays to secure it.
FERC’s next decision will determine implementation
The revised PJM backstop procurement is now a concrete proposal with new financial rules and dates, but not a completed auction. FERC’s treatment of the amended filing, updated load forecasts and the volume of qualifying bilateral contracts will determine how much capacity the operator ultimately seeks and when bidding can proceed.