New York Bulk Battery Storage Awards Reach 950 MW
New York has executed contracts for eight lithium-ion battery projects totaling 950 MW and 4.36 GWh, with commercial operation expected by the end of 2030.
Published · Updated · 4 min read

The New York State Energy Research and Development Authority executed contracts on September 23 for eight lithium-ion projects totaling 950 MW and 4.36 GWh, marking the first awards under the state’s Index Storage Credit program. The New York bulk battery storage portfolio spans six counties from Chautauqua County to the Bronx and Suffolk County.
Seven projects have four-hour durations, while the 140 MW Lighthouse Energy Storage project is designed for eight hours. Contract payments will not begin until each facility reaches commercial operation after securing required permits and local approvals, and all eight projects are expected to enter service by the end of 2030.
The contracts are a material procurement milestone, but they do not establish that the projects are permitted, financed, under construction or operating. NYSERDA’s project fact sheet says the storage portfolio is expected to generate more than $1.6 billion in private investment and more than 500 short- and long-term jobs; those figures remain forecasts.
New York bulk battery storage awards cover eight projects
NYSERDA announced the awards after evaluating 46 proposals representing approximately 6 GW of capacity. Its September 23 announcement pairs the eight storage contracts with 13 separate renewable-energy awards, but the 950 MW storage portfolio has its own capacity, investment and payment terms.
The agency’s contracted-project fact sheet lists the following power and duration ratings:
- Lighthouse Energy Storage in Chautauqua County: 140 MW for eight hours.
- Zenobe Burns in Allegany County: 100 MW for four hours.
- Eastwater Energy Storage in Monroe County: 100 MW for four hours.
- KCE NY 5 in Ulster County: 94 MW for four hours.
- Blue Spruce Storage in Bronx County: 133 MW for four hours.
- Palladium Storage in Bronx County: 123 MW for four hours.
- Holtsville Energy Storage in Suffolk County: 110 MW for four hours.
- KCE NY 37 in Suffolk County: 150 MW for four hours.
Adding the listed capacity-duration products produces 4,360 MWh, or 4.36 GWh, of rated energy capacity. Lighthouse accounts for 1.12 GWh of that total; the remaining seven projects account for 3.24 GWh.
Solar Power World independently reported the 950 MW award total, the eight project names, the four-to-eight-hour durations and the requirement that projects obtain permits and approvals before payments begin.
Contracts defer payments until commercial operation
The Index Storage Credit contracts tie payments to operating projects rather than the award date. NYSERDA says no payments will begin before commercial operation, which leaves development, interconnection, siting, equipment procurement, financing and construction risk with each project before state-supported revenue starts.
That sequencing also separates this procurement from other project milestones. RWE’s recently approved Moerdijk battery, for example, has reached a sponsor investment decision but remains pre-construction. The New York projects have executed state contracts, yet the public documents do not say that every project has reached financial close or a final investment decision.
NYSERDA estimates that the portfolio will add about eight cents per month to an average residential utility bill and provide reliability value in 2030 comparable to roughly 900 MW of fossil-fuel peaking capacity. Both figures are state estimates, not measured outcomes. Actual customer costs and grid performance will depend on project completion, contract settlement, dispatch and system conditions.
New safety rules apply before operation
All eight projects will use lithium-ion technology and must comply with New York storage-safety codes that took effect January 1, 2026. The state’s battery storage guidebook says covered projects must undergo peer review for fire-code compliance while local authorities retain permitting and approval powers.
The contracts require first-responder training, site-safety measures and emergency-response plans. Those safeguards matter because an award does not remove operational hazards associated with large lithium-ion installations. The recent Moss Landing battery fire involved a different facility and jurisdiction, but it underscores why project-specific design, review, emergency planning and operating performance should be evaluated separately.
NYSERDA says the selected storage projects are expected to spend more than $90 million in underserved communities. The agency has not yet published complete construction schedules, equipment suppliers, financing structures, interconnection milestones or individual contract prices in the documents reviewed.
Permits and construction are the next tests
The next verifiable milestones will be local approvals, interconnection progress, financing decisions, construction starts and commercial-operation dates. NYSERDA plans to issue a second annual bulk-storage request for proposals by the end of 2026 as part of a three-solicitation effort to procure 3 GW.
For now, the New York bulk battery storage portfolio should be described as contracted and pre-construction. The September 23 awards establish projects, ratings and a payment framework, while delivery of the planned 950 MW and 4.36 GWh remains contingent on permitting, financing, construction and commissioning by the end of 2030.