Maamba Solar Begins Commissioning With First Zambia Grid Power

Maamba Solar’s 100 MWac photovoltaic plant has injected its first electricity into Zambia’s grid, beginning commissioning before full commercial operation.

Jonas Muthoni

Published · 4 min read

Rows of photovoltaic panels mounted on single-axis trackers at a utility-scale solar facility in India. - Maamba Solar commissioning

Maamba Solar Energy Limited began injecting electricity from its 100 MWac photovoltaic plant into Zambia’s national grid on September 24, starting the project’s commissioning phase in Maamba, Southern Province. The milestone moves the $90 million facility from construction into grid testing before full commercial operation.

The Maamba Solar commissioning program covers a utility-scale plant built with bifacial modules on single-axis trackers, a dedicated 330 kV substation and associated interconnection equipment. Its entire output is contracted to state utility ZESCO under a 20-year power purchase agreement.

First power is a material project milestone, but it does not mean the facility has completed commissioning or begun full commercial operation. The plant must still pass synchronization, reliability, performance and grid-response tests.

Maamba Solar commissioning starts with first grid injection

ZCCM Investments Holdings announced the milestone in a September 25 project update. The state-backed investment company owns 35% of Maamba Solar Energy Limited, while Nava Global PTE Limited, the international arm of India-listed Nava Limited, owns the remaining 65%.

The project sits in Maamba in Sinazongwe District, next to existing Maamba thermal-power operations. Its location allows the solar facility to connect through dedicated high-voltage infrastructure while adding a different generation source at an established energy site.

A detailed regulatory announcement lists the equipment now subject to testing: modules, tracking systems, inverters, the medium-voltage collection network, protection and control systems, meters, supervisory control and data acquisition equipment, communications and grid-interconnection facilities.

Bifacial modules can collect light on both sides, while the trackers rotate the panel rows through the day. The developer has not disclosed the plant’s direct-current module capacity, expected annual generation, capacity factor, module supplier, inverter supplier or final commercial-operation date.

First power does not equal commercial operation

The September 24 grid injection demonstrates that part of the plant can produce and export electricity. Commissioning must now verify that the complete facility performs within technical, contractual and grid-code requirements across a range of operating conditions.

ZCCM-IH said the remaining work includes synchronization, reliability and performance verification and confirmation of the plant’s response to grid requirements. The company did not provide a timetable for completing those tests or state how much of the 100 MWac rating was exported during the first injection.

PV Magazine independently reported the project’s capacity, ownership, location, investment and 20-year ZESCO contract. Its report described the plant as commissioned, but ZCCM-IH’s controlling announcement is more precise: the facility has entered commissioning and still faces tests before full commercial operation.

That distinction also separates Maamba from projects where all commissioning work has ended. Microgrid Media’s coverage of a 322 MWp Indian solar portfolio, for example, concerned a completed commissioning milestone rather than the start of the test phase.

Twenty-year ZESCO contract supports the project

The 20-year power purchase agreement gives Maamba Solar a contracted buyer for its output. The public announcement does not disclose the tariff, dispatch provisions, deemed-generation terms, payment security or curtailment allocation, so the commercial effect of those terms cannot be independently assessed from the released documents.

The approximately $90 million investment equates to about $900,000 per MWac of nameplate capacity. That simple ratio is not a levelized cost of electricity and does not reveal the capital structure, financing rate, operating costs or expected energy production.

An Energy Regulation Board project review reported on September 17 that Maamba Solar was among eight Zambian power developments being monitored for construction progress, regulatory compliance and grid-evacuation infrastructure. The first-power announcement now provides a later, independently traceable project milestone.

ZCCM-IH says the plant can diversify a system exposed to hydropower variability, especially if El Niño conditions reduce water availability. That resilience claim is forward-looking. The actual contribution will depend on completed commissioning, daytime output, network availability, curtailment and how ZESCO operates the wider system.

What comes next at Maamba

The next verifiable events are completion of plant-wide testing, confirmation that the full rated output can be exported, regulatory acceptance and a declared commercial-operation date. Operating data will then show actual energy production, availability and grid performance.

The Maamba project is larger than the 20 MW solar plant inaugurated in Comoros earlier in September, although the Comoros development also includes battery storage and serves a different island system. Maamba has no announced battery component in the documents reviewed.

Until the remaining tests are complete, the Maamba Solar commissioning milestone should be described as first power and entry into the commissioning phase. The project is connected and exporting electricity, but full commercial operation has not yet been confirmed.

Jonas Muthoni

Jonas Muthoni

Jonas Muthoni is Editor-in-Chief of Microgrid Media, where he oversees reporting and analysis on microgrids, energy storage, distributed energy resources, data center power demand, grid modernization, resilience, renewable energy, and electricity policy and markets. His work focuses on the infrastructure, technologies, and regulatory developments reshaping the power system. As Editor-in-Chief, Jonas leads Microgrid Media’s editorial strategy and standards, including story selection, source verification, technical accuracy, and the development of original reporting and analysis. His coverage draws on regulatory filings, government records, utility and company disclosures, technical documentation, and independent industry sources to explain significant developments across the evolving energy system.