MicrogridMedia

GridStor Acquires White Tank Battery Project to Help Arizona Handle Fast Power Needs

Jonas Muthoni

Published · 3 min read

GridStor, a developer and operator of large battery energy storage systems, has bought the White Tank project in Arizona. It is a 100 MW / 400 MWh battery energy storage system (BESS). The seller is Strata Clean Energy. The project sits in Maricopa County. Its job is to help Arizona Public Service (APS) deliver power during peak times. 

Contract, Timeline & Support

  • It has a 20-year tolling agreement with APS. Under this, APS can charge and discharge the battery as needed. 
  • Commercial operations are expected in the first half of 2027. 
  • Strata Clean Energy will keep a consultative role until the system starts operating commercially. 

Technology Partner

The batteries for White Tank will come from e-STORAGE, part of Canadian Solar. The project will use SolBank 3.0 battery enclosures. About 120 battery enclosures are involved. 

Why This Matters for Arizona

Arizona’s power demand is growing fast. Hot summers, more people, and more data centers all add extra load. APS and other utilities set new peak demand records recently. 

Battery storage helps in these ways:

  • Stores electricity when production is high.
  • Delivers power in evening peaks when solar drops.
  • Helps grid reliability when demand is unpredictable.

GridStor’s Growth and Pipeline

GridStor is relatively new, founded in 2022. It is backed by Goldman Sachs Asset Management. 

This White Tank deal is its fourth acquisition in the past 12 months and its second in Arizona. 

GridStor now manages a development/construction pipeline of over 5 GW of battery storage projects across the western and central United States. 

Quick Facts Table

ItemDetails
Project NameWhite Tank
Size100 MW / 400 MWh
LocationMaricopa County, Arizona
BuyerGridStor
SellerStrata Clean Energy
Off‐takerArizona Public Service (APS), via 20‐year tolling agreement
Technology ProviderCanadian Solar’s e-STORAGE (SolBank 3.0 enclosures)
Online TargetFirst half of 2027
Strata’s RoleConsultative until commercial operations
GridStor’s PipelineOver 5 GW under development or construction

Challenges & Opportunities

There are challenges. For example:

  • Building and interconnecting large systems takes time.
  • Supply chain issues can delay battery parts.
  • Financing and permitting often slow progress.

But the opportunities are strong. Arizona has space, strong solar resources, and urgent need for reliable power. Projects like White Tank help bridge gaps in supply. Also, tolling agreements give clear revenue. That makes it easier to get funding. 

Related Projects

Arizona already has big recent battery storage projects. One is the Papago Storage facility, with 1,200 MWh capacity, developed by Recurrent Energy. It is in Maricopa County as well. It joined the grid earlier in 2025. 

What Comes Next

GridStor will need to finish design, engineering, and construction. Then, test and commission the facility. It must meet safety, performance, and regulatory standards. If all goes well, White Tank will begin full commercial operations in early 2027. By then, it will help APS meet evening peaks and power disruptions. It will also help smoother energy flow with rising solar generation.

Conclusion

The White Tank project signals a strong shift toward battery storage in Arizona. GridStor’s purchase shows that investors see value in batteries right now. With a long contract, modern technology, and strong demand, White Tank is well-placed to help keep lights on when people need them most.

Jonas Muthoni

Jonas Muthoni

Jonas Muthoni is Editor-in-Chief of Microgrid Media, where he oversees reporting and analysis on microgrids, energy storage, distributed energy resources, data center power demand, grid modernization, resilience, renewable energy, and electricity policy and markets. His work focuses on the infrastructure, technologies, and regulatory developments reshaping the power system. As Editor-in-Chief, Jonas leads Microgrid Media’s editorial strategy and standards, including story selection, source verification, technical accuracy, and the development of original reporting and analysis. His coverage draws on regulatory filings, government records, utility and company disclosures, technical documentation, and independent industry sources to explain significant developments across the evolving energy system.