UK Grants Consent for 500 MW Green Hill Solar and Storage Project

The UK has approved the proposed 500 MW Green Hill Solar Farm, including battery storage and a connection to National Grid’s Grendon substation.

Jonas Muthoni

Published · 3 min read

Solar panels at London Road Solar Farm in North Northamptonshire, representative of the proposed Green Hill Solar Farm region - Green Hill Solar Farm

The UK government has granted development consent for the proposed Green Hill Solar Farm, authorizing a project with up to 500 megawatts of ground-mounted solar generation, battery energy storage and a grid connection spanning parts of Northamptonshire and Milton Keynes.

The Planning Inspectorate announced the decision on October 8. The approval is a major planning milestone, but it is not the same as a construction start or commercial operation. The developer must still complete detailed design, agreements and planning requirements before work can begin.

Consent covers solar, storage and a grid connection

The approved scheme comprises nine areas of solar photovoltaic generation, battery energy storage systems and the infrastructure needed to connect to the national electricity network at National Grid’s Grendon substation.

According to the developer’s October 8 project update, the site extends across the administrative areas of West Northamptonshire Council, North Northamptonshire Council and Milton Keynes City Council. The solar component is designed for generating capacity of up to 500 MW.

The official government announcement confirms that energy storage forms part of the consented development, but it does not specify the battery’s megawatt-hour capacity, discharge duration, chemistry or equipment suppliers. Solar Power Portal reports a 500 MW battery power rating. Without a published energy-capacity figure, that rating does not establish how long the system could discharge at maximum output.

The decision follows a national infrastructure examination

Green Hill Solar Farm Limited submitted its Development Consent Order application on May 23, 2025. The Planning Inspectorate accepted it for examination on June 19, 2025, then ran a six-month examination in which local communities, authorities, statutory consultees and other interested parties could provide evidence.

The Examining Authority sent its recommendation to the Secretary of State on July 8, 2026. The government says Baroness Curran made the final decision on behalf of the Energy Secretary’s legal authority. Green Hill was the 114th energy application decided among 182 applications examined by the Planning Inspectorate at the time of the announcement.

The milestone differs from the procurement stage described in Microgrid Media’s coverage of the Ekrukh floating solar and battery proposal. Green Hill has secured its principal development consent, while detailed delivery work remains ahead.

Environmental commitments will need delivery

The developer says consultation feedback changed landscaping, biodiversity measures and public-rights-of-way proposals. It has committed to at least 47% biodiversity net gain in habitat units, more than 14.4 hectares of green corridors and woodland planting, 50.7 kilometers of new or improved hedgerows, and more than 18 kilometers of permissive paths.

Those figures are developer commitments rather than independently measured outcomes. Their value will depend on final designs, compliance with the consent order and performance over the project’s operating life.

What happens next for Green Hill Solar Farm

The developer says the project now moves from planning toward delivery. Near-term work includes detailed design, final agreements and the discharge of planning requirements before construction begins. Its October 8 announcement did not provide a final investment decision, financing close, construction-start date, equipment award or commercial-operation date.

That distinction matters when comparing the proposal with operating assets such as the 20 MW Comoros solar-and-storage portfolio, which has already been inaugurated. Development consent makes Green Hill Solar Farm legally more advanced, but it does not yet make its solar panels or battery available to the grid.

The project’s next material milestones will be evidence that the consent conditions are being discharged, delivery contracts are in place and construction has formally started. Until then, the approved 500 MW solar capacity and associated storage should be described as proposed rather than operational.

Jonas Muthoni

Jonas Muthoni

Jonas Muthoni is Editor-in-Chief of Microgrid Media, where he oversees reporting and analysis on microgrids, energy storage, distributed energy resources, data center power demand, grid modernization, resilience, renewable energy, and electricity policy and markets. His work focuses on the infrastructure, technologies, and regulatory developments reshaping the power system. As Editor-in-Chief, Jonas leads Microgrid Media’s editorial strategy and standards, including story selection, source verification, technical accuracy, and the development of original reporting and analysis. His coverage draws on regulatory filings, government records, utility and company disclosures, technical documentation, and independent industry sources to explain significant developments across the evolving energy system.