Black Hills Sets 2.7 GW Plan for Google Cheyenne Private Microgrid
Black Hills and Google signed definitive agreements for a Cheyenne power plan combining up to 590 MW of utility service with about 2.1 GW of managed resources.
Published · 3 min read

Black Hills Corp. and Google have executed definitive agreements for electricity service to a planned data center in Cheyenne, Wyoming. The package calls for a 2.7 GW resource mix, including reserves, and combines up to 590 MW of utility service with approximately 2.1 GW of Wyoming-based third-party resources managed through what Black Hills calls a privately managed microgrid.
The Google Cheyenne private microgrid is a contracted power architecture rather than an operating facility. Black Hills said service is expected to begin in late 2027 and ramp toward peak requirements in 2030, so the announced figures should not be treated as current data-center load or completed generation.
Google Cheyenne private microgrid combines utility and third-party resources
Black Hills announced the agreements on October 6 and said they became effective September 30. The company identified a Large Power Contract Services Agreement and a Generation Facilities Agreement running through 2048.
Under the announced structure, Black Hills would provide up to 590 MW of grid-connected service. The company plans to build 564 MW of new natural-gas generation at its existing Cheyenne Prairie Generating Station through a nonregulated affiliate, with the remaining 26 MW supplied from market purchases and Black Hills Energy’s retail tariff.
Black Hills would also manage about 2.1 GW of contracted third-party resources located in Wyoming. The company did not identify those suppliers or publish the full generation mix in the announcement. Because the 2.7 GW total includes reserve capacity, it is not equivalent to a statement that the data center will draw 2.7 GW continuously.
Reuters independently confirmed the agreements and investment plan, reporting that Black Hills expects to spend $1.8 billion from 2027 through 2029 on new generation capacity for the project.
Company says the contract shields other utility customers
Black Hills says the agreements are structured so Google bears the costs of serving the planned facility rather than shifting them to other utility customers. The announcement points to customer-funded infrastructure, collateral and other contractual protections, but the practical outcome will depend on implementation, regulatory treatment and the final cost of the facilities.
Google has agreed to provide $399 million in refundable advances for long-lead equipment under a generation-reservation arrangement. Black Hills expects to reimburse those advances by June 30, 2027. The company also projects roughly $150 million in net income from the project in 2030 and $2.4 billion in unlevered free cash flow through 2048. Those are forward-looking company estimates, not guaranteed outcomes.
Permitting and transmission work remain part of the schedule
Several infrastructure steps are already in the regulatory process. Black Hills said Wyoming regulators approved a certificate for the Robinson substation in May 2026, while an industrial-siting permit was filed in July and an air-quality permit was approved in August. A certificate application for the South Cheyenne transmission project was filed in September, and additional transmission filings are planned.
The word “microgrid” also requires care. Black Hills uses it for the privately managed 2.1 GW resource portfolio, but the announcement does not establish that the Google campus will be able to disconnect from the wider grid and operate as an electrical island. Microgrid Media’s guide to data center microgrids explains that coordinated resources may remain grid-connected and that islanding capability depends on the actual controls, protection and generation design.
The arrangement differs from fully behind-the-meter campuses. Microgrid Media’s coverage of Project Matador’s private gas-generation fleet describes a developer-owned power system planned alongside data-center infrastructure. In Cheyenne, a regulated utility would supply part of the load and manage a much larger set of contracted resources.
The signed agreements are the material new development
Black Hills had previously discussed the prospective Cheyenne data-center opportunity, but the October disclosure confirms signed definitive agreements, a service structure and a capital program. That moves the proposal beyond a preliminary reservation without making the generation, transmission or data center operational.
For the Google Cheyenne private microgrid, the next decisive evidence will be permit decisions, financing and construction progress, named third-party resources, initial power delivery and later confirmation of peak service. Until then, the 2.7 GW plan is a contracted roadmap with material execution and regulatory work still ahead.