Entergy New Orleans Grid Hardening Starts With $2.05M Grant

Entergy New Orleans has begun a Leonidas-area grid-hardening project covering 94 distribution poles and 1.6 miles of network, backed by a $2.05 million federal grant.

Jonas Muthoni

Published · 3 min read

Utility poles and overhead distribution lines along Leonidas Street in New Orleans. - Entergy New Orleans grid hardening

Entergy New Orleans broke ground on a federally supported distribution-grid project in the Leonidas and Hollygrove areas on September 22, beginning work intended to reduce the frequency and duration of outages for homes, businesses and critical infrastructure.

The Entergy New Orleans grid hardening project will replace or upgrade approximately 94 distribution poles, strengthen about 1.6 miles of the local network and add targeted vegetation management. More than 1,900 customers are expected to benefit, and the work is scheduled to be completed within two years.

A $2.05 million U.S. Department of Energy grant will cover part of the cost. Entergy has not disclosed the project’s total cost, the utility’s remaining contribution or a detailed construction schedule, so the grant amount should not be presented as the full value of the work.

Entergy New Orleans grid hardening begins in Leonidas

Entergy announced the construction start in a September 22 release. The utility said the project will replace roughly 94 poles and harden a 1.6-mile section of distribution infrastructure while trimming trees and foliage that could contact service lines.

Company and federal officials held the groundbreaking near a Sewerage and Water Board of New Orleans facility. Local reporting by FOX 8 identified that facility as one of the critical-service customers expected to benefit from the work.

The local report also supplied a completion target that was not included in Entergy’s announcement: the work is expected to finish within two years. Entergy said the portion of project cost not covered by the federal grant is already incorporated into customer rates and will not produce a separate rate increase for this project.

Federal grant supports a state-selected project

The award comes through the Department of Energy’s Grid Resilience State and Tribal Formula Grants program. DOE describes the program as a five-year funding mechanism for projects intended to strengthen electric systems against severe storms, wildfires and other disruptive events.

Louisiana’s Department of Conservation and Energy selected the Entergy project as one of 13 initiatives funded through the state. Entergy’s release did not identify the other recipients or disclose the state’s complete allocation for that group.

Officials estimate the Leonidas work could avoid $7.4 million in outage-related and restoration costs over 50 years. That figure is a projection attributed to Entergy, not a guaranteed saving. Its eventual accuracy will depend on storm exposure, outage performance, equipment life, maintenance and the method used to value customer interruptions.

Poles and vegetation address different outage risks

Replacing poles to current wind standards is intended to reduce structural failures during high-wind events. Targeted vegetation management addresses another failure pathway by reducing the likelihood that branches or trees will damage conductors and service equipment.

Neither measure makes the circuit outage-proof. Flooding, debris, upstream transmission failures, equipment faults and damage beyond the project boundary can still interrupt service. The clearest performance test will be whether the upgraded area records fewer or shorter outages than comparable periods before construction.

The project is smaller than Entergy Louisiana’s Jefferson Parish grid-hardening program, which covers thousands of structures and hundreds of miles outside Orleans Parish. The Leonidas project is a separate, neighborhood-scale investment involving Entergy New Orleans and a federal formula grant.

Evidence from other utilities shows why post-construction measurements matter. Microgrid Media reported that upgraded New Jersey circuits recorded company-reported reliability improvements after pole replacements and other distribution work, while noting that weather, equipment and circuit configuration can also influence results.

What happens next

The September 22 milestone confirms that physical work has begun, rather than only being proposed or funded. The next verifiable stages are pole replacement, completion of the 1.6-mile hardening scope, implementation of vegetation work and final energization of upgraded equipment.

Entergy has not published a pole-by-pole schedule, wind-rating specification, contractor list or baseline outage metrics for the affected circuit. Those details will be important for evaluating execution and later performance.

Until construction is complete, the Entergy New Orleans grid hardening project should be described as underway. Its projected reliability and cost benefits remain estimates that will require operating data after the upgraded assets enter service.

Jonas Muthoni

Jonas Muthoni

Jonas Muthoni is Editor-in-Chief of Microgrid Media, where he oversees reporting and analysis on microgrids, energy storage, distributed energy resources, data center power demand, grid modernization, resilience, renewable energy, and electricity policy and markets. His work focuses on the infrastructure, technologies, and regulatory developments reshaping the power system. As Editor-in-Chief, Jonas leads Microgrid Media’s editorial strategy and standards, including story selection, source verification, technical accuracy, and the development of original reporting and analysis. His coverage draws on regulatory filings, government records, utility and company disclosures, technical documentation, and independent industry sources to explain significant developments across the evolving energy system.