Critical Loop Plans 25 MW Industrial Microgrid to Bridge California Grid Delays
Critical Loop and SRG Commercial have announced a 25 MW hybrid microgrid for a Southern California industrial campus, including 60 MWh of batteries to bridge a delayed utility upgrade.
Published · 3 min read

Critical Loop announced plans on October 27 for a 25 MW hybrid microgrid serving an SRG Commercial industrial campus in Southern California, where a planned utility upgrade will not arrive in time for a manufacturer’s anticipated operating schedule. The project is intended to provide temporary power capacity while the site awaits its permanent grid connection.
The Critical Loop microgrid design includes 12 MW of battery power with 60 MWh of storage, alongside existing utility service and dedicated emergency generation. Critical Loop describes the arrangement as an 18-month bridge solution, with a target of delivering the overall 25 MW system within nine months of contract execution.
How the 25 MW industrial microgrid is designed to work
According to Critical Loop’s October 27 announcement, the campus has approximately 7 MW of firm grid capacity and another 2 MW of flexible service. The planned microgrid is designed to manage the gap between that available supply and the tenant’s higher power requirements.
Battery storage is expected to supply power when site demand exceeds the available utility connection. Onsite generation would address remaining requirements, while 3.5 MW of dedicated emergency generation is intended to provide additional backup capability.
The announced figures describe different functions within the power system. The 25 MW figure represents the proposed overall system capacity, while 12 MW describes battery discharge power and 60 MWh describes stored energy. These ratings should not be added together as if they were separate, continuously available sources of electricity.
Critical Loop microgrid controls address limited grid imports
The project will use Critical Loop’s CLB-5100 power system and Cygnus controller software. The company says the controller manages battery charging and discharging against site loads while enforcing grid-import limits.
That coordination matters for facilities whose electrical demand can exceed the capacity of their existing utility connection. A controller must manage available grid power, battery state of charge and onsite generation without allowing the site’s imports to exceed applicable limits.
Microgrid Media has previously explained how microgrid interconnection requirements shape the design of systems that operate alongside a utility network. The SRG project illustrates a related challenge: using local resources to support an industrial load while permanent grid infrastructure remains constrained.
A two-year partnership extends beyond one campus
Alongside the initial project, SRG Commercial named Critical Loop its preferred microgrid partner across Southern California for two years. The agreement creates a framework for considering similar solutions at other properties, although the announcement does not identify additional contracted campuses or their capacities.
Critical Loop’s company news archive also documents an earlier announcement concerning its controller’s certification and interoperability testing. Those prior technical milestones are separate from the October 27 industrial deployment announcement.
The initial project’s operating timetable remains an important distinction. Critical Loop says its solution is designed to meet the tenant’s early-2027 power requirements, but the announcement does not independently establish that the entire 25 MW system has been energized or commissioned.
What to watch before commissioning
The next meaningful checkpoints for the Critical Loop microgrid will be equipment installation, confirmed energization, the operation of its storage and generation resources, and eventual transition to the permanent utility upgrade.
The project is a concrete example of an industrial developer attempting to manage a grid-connection delay with local power infrastructure. Its ultimate performance, costs and operating benefits will depend on execution and actual operating results rather than the announced design alone.