CAISO Approves Flexible Large-Load Interconnection Proposal

CAISO’s board has approved a flexible interim interconnection proposal for data centers and other large loads, with a federal filing due by November 16.

Jonas Muthoni

Published · 4 min read

Microgrid Media editorial illustration of the CAISO large-load interconnection proposal, with a data center, manufacturing facility, substations and transmission lines.

The California Independent System Operator’s board approved a CAISO large-load interconnection proposal on October 28 that would create a flexible interim pathway for data centers, manufacturers and other major electricity users to connect before all related network upgrades are complete.

The proposal is not yet an effective federal tariff. CAISO plans to file it with the Federal Energy Regulatory Commission by November 16, after which FERC will decide whether the package satisfies its June order on reliable large-load service and protection against cost shifting.

Microgrid Media’s earlier coverage of the FERC large-load proceeding covering six regional markets explains the federal order that produced CAISO’s current filing process. The board vote is a new regional response within that existing docket, not a new national rule.

The CAISO large-load interconnection proposal advances to FERC

The California ISO’s October 28 announcement confirms board approval and identifies flexible interim load interconnection as the central mechanism.

Under that framework, a qualifying large load could receive transmission service while associated network upgrades are still being completed, but only with enforceable operating flexibility tied to grid conditions and constraints.

That is different from an unconditional right to consume the facility’s maximum requested load at all times. The interim pathway would trade some operating certainty for an earlier connection while the permanent grid work proceeds.

Reuters independently confirmed the board action, November filing deadline and proposal’s focus on faster connections without compromising reliability or shifting costs to other customers.

Flexibility would be enforceable, not voluntary

CAISO says participating facilities would face operational requirements intended to give the grid operator visibility and control when transmission constraints emerge.

The proposal calls for hourly forecasts, telemetry and other operating data. It also establishes communication protocols that would allow CAISO to coordinate with the participating transmission owner to disconnect a large load remotely when necessary to maintain transmission reliability.

Those provisions matter because data centers and advanced manufacturing facilities can add tens or hundreds of megawatts at a single location. Serving a project before all network upgrades are complete can be workable only if the interim load remains within the limits established by actual grid conditions.

Microgrid Media’s reporting on UC San Diego’s flexible AI data-center load demonstration provides a technology-level comparison: that research project tests whether computing demand can respond to grid needs, while CAISO’s proposal would establish system-level service and operating rules.

Monthly review windows target shorter study timelines

The proposal would create a monthly CAISO review window for transmission additions or upgrades associated with large loads that fall outside the normal transmission-planning cycle.

CAISO says the change is designed to accommodate FERC’s 60-to-90-day expectation for participating transmission owners’ load-interconnection studies. A more frequent review process could prevent an otherwise mature project from waiting for the next annual planning cycle before required upgrades are evaluated.

The official large-load initiative record shows that CAISO posted revised draft tariff language on October 26 and received board approval on October 28. It lists the November 16 FERC filing as the next formal milestone.

The timeline does not guarantee a completed interconnection study within 60 days for every project, nor does it establish a date when any particular data center will energize. Project-specific engineering, utility coordination and construction requirements remain separate.

The plan addresses visibility and cost allocation

Beyond interim service, CAISO’s package includes procedures for coordination with utilities on applications, studies, technical standards and operating requirements. It also proposes a framework intended to prevent infrastructure costs from being shifted to customers that did not cause them.

Cost responsibility has become a central issue in large-load regulation. Microgrid Media’s analysis of the Duke Energy large-load tariff settlement in North Carolina explains a different approach built around deposits, upfront funding and minimum billing obligations for qualifying customers.

CAISO is also seeking parallel information for arrangements that combine large loads with co-located generation. Full visibility matters because a facility’s gross demand, on-site supply and net grid withdrawal can create different planning and operational effects.

The board-approved package defers some questions. CAISO identifies future policy work for generating facilities that serve large loads from separate but electrically proximate locations, rather than treating that issue as resolved in the present proposal.

FERC review is the next legal gate

The board vote is a material regulatory milestone, but it does not mean CAISO has already implemented the new service or approved any individual large-load connection under it.

The distinction resembles other bridge-power responses to connection delays. Microgrid Media recently reported that Critical Loop plans a 25 MW California industrial microgrid to serve customers waiting for permanent utility upgrades; CAISO’s proposal instead creates a transmission-service pathway based on enforceable load flexibility.

FERC can accept the filing, reject it, require changes or set additional proceedings. The filed tariff language and any federal order will determine the final obligations, implementation timing and customer protections.

For now, the CAISO large-load interconnection development should be described as a board-approved proposal headed to federal review—not an operating tariff or a blanket approval for new California data centers.

Jonas Muthoni

Jonas Muthoni

Jonas Muthoni is Editor-in-Chief of Microgrid Media, where he oversees reporting and analysis on microgrids, energy storage, distributed energy resources, data center power demand, grid modernization, resilience, renewable energy, and electricity policy and markets. His work focuses on the infrastructure, technologies, and regulatory developments reshaping the power system. As Editor-in-Chief, Jonas leads Microgrid Media’s editorial strategy and standards, including story selection, source verification, technical accuracy, and the development of original reporting and analysis. His coverage draws on regulatory filings, government records, utility and company disclosures, technical documentation, and independent industry sources to explain significant developments across the evolving energy system.